Wednesday, 14 August 2013

THE CAUSE OF DELAY FOR PILING WORK

THE PILING WORK WILL COMMENCE SOON , THE DELAY WAS CAUSED BECAUSE THE PLANS WERE JUST APPROVED BEFOR THE  HARI RAYA HOLIDAYS. THE PILES HAVE BEEN SENT BY THE CONTRACTOR THIS WEEK AND THE PILING WORK WILL COMMENCE ON MONDAY 17 AUGUST 2013

12 AUGUST THE PILES HAVE ARRIVED AT SITE




Wednesday, 17 July 2013

LATEST INFO ON PLAN APPROVAL

FINAL DOCUMENTS - BOMBA APPROVAL AND RC DRAWINGS WILL BE SUBMITTED  TO MBI TODAY     MBI IS EXPECTED TO APPROVE BUILDING PLANS ON 24/07/13 ONLY AFTER THIS WE CAN START PILING WORKS AND GET THE PROJECT MOVING.

OLD STORE BEING DEMOLISHED AND NEW TEMPORARY STORE CONSTRUCTED TO HOUSE ALL THE ITEMS